Local Infrastructure Project Bonds (LIP) 

A number of Snohomish County projects will make it easier for people to get around their neighborhood, to schools, shopping areas and other neighborhoods.The plans include building and repairing sidewalks; widening road shoulders for walking and bicycling; upgrading ADA ramps; and installing crosswalks, traffic signals, and pedestrian-operated beacons.


Projects Completed Using LIP Funding

 Location  Description  Status
 3rd Ave SE - 130th St SE
Sideway - 100% design  Complete 
35th Ave SE Pedestrian improvements Complete 
39th Ave SE Sidewalk from 220th St SE to 221st Pl SE Complete
51st Ave SE Sidewalk near Seattle Hill Elem Complete
84th St NE/115th Ave NE
 
Intersection improvement - 60% design report and right of way plan  Complete 
Bev Park Rd & Gibson Rd Traffic Signal Complete
Cathcart Way & Puget Park Dr Traffic Signal Complete
Centennial Middle School Pathway plus flashing beacon on S. Machias Rd. See photo of the new pathway here. Complete
Cougar Creek Elem School
Dynamic Speed Signs on 11th Ave NE Complete
Discovery Elem School School Crossing Upgrade on Meridian Ave S Complete 
Elgin Way Sidewalk Complete
Fairmont Elem School Dynamic speed signs on Bev-Park Rd Complete 
Jefferson Elem. School Sidewalk along Cadet Way Complete
Jefferson Elem. School Flashing beacon & asphalt pad Complete
Maltby Elem School Shoulder improvements to 99th Ave SE Complete
Manor Way
 
5' shoulder connecting 164th St SW to 156th St S and 
60% design plans for future road section (two-way left turn, bike lanes, sidewalk)
 
Complete 
Mariner High School  Sidewalk on Meridian Ave S
 
Complete
North Creek Trail 
90% design plan and right of way acquisition  Complete
Olivia Park Elem School Walkway on 108th St SW Complete 
Picnic Pt Elem School Curb ramp replacements at 60th Ave W/140th St SW and two school driveways Complete 
Tulalip Schools  Dynamic speed signs on 27th Ave NE  Complete 
Voyager Middle School Dynamic speed signs on 4th Ave W Complete