29th Dr SE - drainage improvements near 17414

Description
The project will replace a deteriorated metal culvert that has created sink holes in the roadway along the west side of 29th Dr. SE, south of Mill Creek. The replacement pipe will be a 30-inch polyethylene reinforced rib plastic pipe. Improvements will occur mainly within the road right-of-way with a short section on an easement adjacent to the roadway. The new culvert will meet Washington State Dept. of Fish and Wildlife fish passage criteria. Snohomish County Road Maintenance will do the work. 

Schedule
Construction is scheduled to start 8/17/2015 and expected to last approximately 3 weeks

Traffic Impact
Appropriate traffic control will be provided to route traffic around the construction site. A two day closure from 7am - 4pm is scheduled for August 25th and 26th.