Snohomish County Public Works is proposing improvements to the Locust Way and Larch Way intersection. These improvements are expected to improve traffic flow and expand mobility for bicyclists and pedestrians. Intersection improvements may include the addition of a traffic signal and two left turn pockets. This project is currently in the design report phase with construction estimated to begin in 2019.

Schedule


  • 2017-2018: Prepare design report, survey, environmental review, right-of-way acquisition and public involvement 
  • 2019- 2020: Estimated construction (pending funding) 

Funding

 
Funding for construction has not been secured yet. More Information on the right-of-way acquisition process can be found on our Before we Build Pamphlet.