Roads Update February 21, 2020

This is a list of projects by contractors, utility companies and Snohomish County Public Works that are currently (or soon to be) affecting travel on roads in unincorporated Snohomish County area.

The Snohomish County Public Works 2018 Annual Report is now available online. See how the projects from last year impact residents' daily lives. 

New icon Projects added in the past 10 days include this symbol.
      

View Projects


To view the list of projects, scroll down the page or use these links.

Links to other Projects


If you don't find the project listed below, check your local city websites or WSDOT for other project information. 

WSDOT

- Construction Information

All County


Arlington - Oso

  • No postings at this time. 

Bothell, Maltby area

  • New icon Filbert Dr, between 197th Dr SE and 196th St SE
    Single lane closure extended Feb 17 - Feb 21, 8am - 4pm. Applied Professional Services - pothole for existing underground utilities in conjunction with North Creek Trail Phase I. #19-117158MS
  • Jonathan Rd,
    Single lane closure extended Feb 12 - Feb 28, 8:30am - 3:30pm. AA Asphalting - patching and paving restoration in conjunction with gas service installation for Coyote Crossing. #19-118047MS
  • Lockwood Rd, at 24118
    Single lane closure extended Feb 13 - Feb 29, 9am - 3pm. AA Asphalting - patching and paving restoration in conjunction with gas service installation. #19-118425MS
  • New icon W. Richmond Rd, in the 21000 block
    Single lane closure northbound Feb 4 - Feb 15, 8am - 4pm. Team Nelson - installing sewer, working either side of WSDOT R/W. #19-118668MS
  • 35th Ave SE, between 18600 - 18400
    Single lane closure extended Jan 27 - Feb 27, 9am - 3pm. CableCom LLC - installing telecommunications equipment for Comcast. #19-112216MS
  • 35th Ave SE, from SR 524 to 180th St SE
    Alternating single lane closure extended Jan 6 - Mar 2, M-F 9:30am - 2:30pm and 7pm - 5am; Sat and Sun 7am - 7pm. PUD - multiple pole relocations. #19-110873MS
  • New icon 41st Ave SE & 148th St SE, at the intersection
    Alternating single lane closure extended through Feb 28, 9am - 3pm. BYK Construction - complete waterline connections, hydrants, curb and gutter and final asphalt for Hamptons at Mill Creek Phase II. #19-110997MS
  • New icon 41st Dr SE, in the 17800 block
    Single lane closure extended Mar 11 - Mar 20, 9am - 3pm. AA Asphalting - patching and paving for plat of Pinedale II. #20-100039MS/
  • 42nd Ave SE, between 20800 and 21000 block
    Alternating single lane closure Jan 27 - Feb 10, 9am - 3pm. PSE/InfraSource Services - tie into existing main and extend, install stubs. Patching and paving restoration work to follow. #20-101158MS
  • New icon 58th Ave SE, between 244th St SE and 238th St SE and on 57th Ave SE to 63rd Ave SE
    Alternating single lane closure Mar 9 - May 15, 9am - 3pm. PSE/InfraSource Services - retiring gas main, patching and paving to follow with AA Asphalting. #20-102368MS/
  • 169th Pl SE, in the 2200 block
    Alternating single lane closure extended Feb 12 - Feb 28, 8:30am - 3:30pm. AA Asphalting - patching and paving restoration following gas service installation. #19-118071MS
  • New icon 188th St SE at 35th Ave SE,
    Single lane closure (westbound) Feb 7, 9am - 3pm. American Electrical Services - disconnecting and the installing, on a new pole traffic signals and pedestrian push button including making all connections in conjunction with 35th AVe SE Phase 2 project. #20-100896MS/
  • 228th St SE, between the 3500 - 3600 block
    Single lane closure (westbound) Oct 10 - Mar 10, 9am - 3pm. BDZ Construction - installing water, sewer and frontage improvements for the plat of Jamison Estates. #19-110821MS

Darrington


  • No postings at this time. 

Edmonds

  • New icon 52nd Ave W, in the 15500 block
    Alternating single lane closure Feb 24 - Mar 24, 9am - 3pm. PSE/InfraSource Services - installing pedestal and connecting power service. #20-102876MS/
  • New icon 160th St SW, in the 5400 block
    Single lane closure Feb 10 - Feb 21, 9am - 3pm. AA Asphalting - patching and paving restoration work. #19-117413MS
  • New icon 228th St SE, between 8400 - 8000 blocks and on 84th Ave W between 22800 - 23300 blocks
    Single lane closure eastbound Feb 13 - Mar 12, 9am - 3pm. CableCom - installing telecommunications equipment for Comcast. #19-111058MS/

Everett

  • Beverly Park Rd, at SR 525 and at 122nd St SW
    Single lane closure northbound will continue through Mar 12, 9:30pm - 4:30am. CableCom - installing telecommunications equipment for Comcast. #19-109613MS
  • New icon Beverly Park Rd, in the 11800 block
    Single lane closure, northbound Feb 7 - Feb 12, 8:30am - 1:30pm. MASTEC North America - installing conduit, vaults and pull fiber cable. #19-111239MS
  • New icon Beverly Park Rd, between Gibson Rd and the 12100 block
    Single lane closure southbound revised Feb 11, 8am - 2pm. Skyline Communications - for 30 concrete trucks to access job site. Flagger will assist trucks to back into the job site and then depart. #19-112242MS
  • New icon York Rd 
    Alternating single lane closure Feb 12 - Feb 24, 9am - 3pm. Aero Construction - replacing storm filters in manholes. #20-101657MS/
  • New icon 3rd Ave SE, and westbound lane of 127th St SE
    Single lane closure Feb 24 - Mar 25, 9pm - 5am. CableCom - installing telecommunications equipment for Comcast. #19-111057MS/
  • New icon 4th Ave W, between 3rd Pl W to just north of 112th St SW and on 112th St SW east of 4th AVe W to the 1200 block
    Single lane closure Feb 21 - Mar 20, 9am - 3pm. CableCom - overlashing fiber to existing strand and installing telecommunications equipment for Comcast. #19-117110MS/
  • 17th Ave W, between Gibson Rd and N Lake Stickney Dr
    Alternating single lane closure Jan 15 - Mar 27, 9:30am - 2pm. Currie Construction - installing storm, sewer and frontage improvements for proposed Keller short plat. #20-100215MS
  • 25th Ave SE, in the 12700 block
    Alternating single lane closure will continue through Mar 6, 8:30am - 3:30pm. Shell Excavating Inc for Lance Harvey Trucking & Excavating Inc - installing frontage improvements for a proposed short plat. #19-118192MS
  • 26th Dr SE, 10433 and 10507
    Alternating single lane closure extended Feb 3 - Feb 28, 8:30am - 4pm. PSE/InfraSource Services - installing new gas service with patching and paving restoration to follow. #18-151824MS
  • New icon 130th St SE
    Alternating single lane closure Mar 9 - Mar 20, 9am - 3pm. AA Asphalting - patching and paving restoration work on an emergency gas leak repair. #20-102333MS/
  • New icon 131st SE, in the 1100 block
    Single lane closure extended Feb 13 - Mar 1, 8:30am - 4pm. Tony Gusman Excavating - installing frontage improvements for Ramalah. #19-102046MS/ 
  • New icon 132nd St SW, in the 700 block
    Alternating single lane closure Mar 9 - Mar 20, 9am - 3pm. PSE/InfraSource Services - installing gas service to a residence with patching and paving restoration to follow by AA Asphalting. #20-012348MS/

Gold Bar


  • No postings at this time. 

Granite Falls

  • No postings at this time. 

Index

  • No postings at this time. 

Lake Stevens

 
  • Machias Cutoff, 20th St SE, Williams Rd and S Machias Rd
    Signage placement and detours Nov 7 - May 1, 2020. City of Lake Stevens - constructing a multi-use path on S. Lake Stevens Rd between 18th St SE and East Lakeshore Dr. Contact :
    City of Lake Stevens, Aaron Halverson, 425-622-9447, #19-108924MS
  • New icon 84th St NE, between the 11200 - 12300 blocks
    Alternating single lane closure continues Feb 17 - Mar 6, 8:30am - 3:30pm. Frontier Communications - remove poles and relocate, transfer aerial facilities in advance of the 115th Ave NE county project. #19-114683MS/

Lynnwood

  • Alder Way, in the 17700 block
    Alternating single lane closure Nov 19 - Mar 20, 8:30am - 4pm. Land Dirt Pipe LLC - installing frontage improvements for Dawson Place. #19-117272MS
  • New icon Ash Way, between 16800 and Alder Way 
    Single lane closure Feb 13, revised hours 9am - 3pm.PUD. #18-124810MS/
  • New icon Beverly Park Rd, in the 12400 block
    Single lane closure, northbound Feb 24 - Mar 6, 9pm - 4am. Ismael's Construction - locate and install water taps off existing AWWD water line. #19-118232MS/
  • New icon Damson Rd, in the 20800 block
    Single lane closure, northbound Feb 17 - Mar 31, 9am - 3pm. Universal Land Construction - installing frontage improvements. #20-102385MS/
  • New icon Larch Way, in the 16200 block
    Alternating single lane closure Feb 12 - Feb 28, 9am - 3pm. Medallion Homes - control to allow trucks to pour a concrete driveway. #19-118817MS/
  • Locust Way, in the 1600 block
    Alternating single lane closure Feb 13 - Feb 27, 9am - 3pm. PSE/InfraSource Services - tie into existing service to serve the plat of Aspen Heights. Patching and paving restoration to follow. #20-101195MS
  • Locust Way, in the 1700 block
    Alternating single lane closure will continue through Mar 27, 8:30am - 4pm. Plats Plus Inc - installing right of way improvements for the proposed plat of Aspen Heights. #19-113745MS
  • New icon Motor Pl,  at 16002
    Single lane closure extended Feb 13 - Feb 28, 9am - 3pm.  AA Asphalting - patching and paving restoration work after gas installation at a residence. #19-118468MS
  • Motor Pl, in the 16300 block
    Single lane closure, northbound Jan 13 - Feb 25, 9am - 3pm. Kirtley-Cole Associates - replacing storm drain and installing frontage improvements. #19-116638MS
  • New icon 14th Pl W, east of S Lake Stickney Dr
    Alternating single lane closure Mar 9 - Mar 20, 9am - 3pm. PSE/InfraSource Services - tie into existing lines for plat of Creekside Grove with patching and paving restoration work to follow by AA Asphalting. #20-102359MS/
  • New icon 146th St SW
    Single lane closure extended Feb 4 - Feb 28, 9am - 3pm. TD Alskog Inc - installing utilities water main and frontage improvements. #19-102893MS
  • New icon 146th St SW, in the 100 block
    Alternating single lane closure Feb 4 - Feb 14, 9am - 4pm. Westerly - installing water, sewer, utilities and frontage improvements for the Greenstone Estates short plat. #19-103345MS
  • 150th St SW
    Single lane closure continues Feb 12 - Feb 28, 9am - 3pm. AA Asphalting - patching and paving restoration work after gas main extension. #19-117453MS
  • New icon 155th St SW, east and west of 2nd Ave W
    Single lane closure Feb 10 - Apr 30, 8am.BDZ Construction - installing utilities, storm facilities and frontage improvements for the Milagro project. #20-102157JML/
  • New icon 164th St SW, in the 4700 block
    Single lane eastbound closure Feb 19 - Mar 31, 8am - 4:30pm. Absolute Excavating - installing storm drain, sewer, utilities and frontage improvements for Keeler Vista Townhouses. #20-100103MS/
  • New icon 202nd Pl SW, in the 1600 block
    Single lane closure westbound Mar 16 - Apr 3, 9am - 3pm. PSE/InfraSource Services - replacing gas main with patching and paving restoration to follow. #20-102353MS/

Marysville/Tulalip/Lakewood

  • Marine Dr, north of 27th Ave NE and at east and west ends of bridge #419
    Work restarts Jan 6 - Feb 14, 8am - 4pm. During the week of January 6-10 two work zones will be allowed on Marine Drive between 27 Ave NE and 31 Ave NE with hours of work for this week only reduced to 8:30 – 3:30 to allow AM and PM peak hour traffic to proceed unrestricted through the area before the daily dual work zones are set up. This should complete everything but final paving, Reece Construction - final connections for the Tulalip Utilities Expansion project. Final paving is weather dependent. #19-116992JML

Mill Creek

  • No postings at this time. 

Monroe

  • High Bridge Rd, between 20500 - 15300 blocks
    Single lane closure, northbound Jan 14 - Feb 21, 8:30am - 4pm. Shell Excavating - installing guard rail along the east side of High Bridge Rd for the proposed plat of Highbridge Estates. #20-101015MS
  • Old Owen Rd, between 22400 - 23800 blocks
    Single lane closure Jan 31 - Feb 28, 9am - 3pm. CableCom LLC - proof and pull cable to existing poles. #19-113003MS
  • Tualco Rd, SW of Monroe city limits
    FULL ROAD CLOSURE will continue through Apr 1 - Apr 15. Snohomish County Public Works will replace #155 Riley Slough Bridge. A 1.5 mile detoured via Tulaco Loop Rd will be in place. There will be no access across the bridge during construction. #19-103299MS
  • New icon Woods Creek Rd at the intersection with Yeager Rd and Bollenbaugh
    Hill Rd
    Single lane closure northbound Feb 18 - Feb 21, 8:30am - 4:30pm. PUD - utility work and tree trimming. #19-116497MS/

Mukilteo

  • No postings at this time. 

Snohomish/Maltby

  • New icon Airport Way, in the 9500 block
    Single lane closure northbound Feb 10 - Mar 13, 9am - 3pm. CableCom - installing telecommunications equipment. #19-117076MS
  • Broadway Ave, on 206th St SE between 87th Ave SE and Broadway and between 20600 - 20100 blocks
    Single lane closure, westbound Feb 3 - Mar 5, 8:30am - 4:30pm. CableCom LLC - installing telecommunications equipment for Comcast. #19-114061MS
  • Broadway Ave, in the 17700 block
    Alternating single lane closure Feb 3 - Feb 21, 9am - 3pm. PSE/InfraSource Services - installing gas service to a residence. Patching and paving restoration to follow. #20-101527MS
  • Fales Rd, at 19801
    Single lane closure continues Feb 12 - Feb 28, 9am - 3pm. AA Asphalting - patching and paving restoration in conjunction of gas service installation. #19-118428MS
  • New icon Homes Acres Rd, north of Swans Slough Rd
    One day FULL Road closure Feb 25, 9am - 3pm. Olympic Pipeline - repairs at two pipeline sites. #20-102662HN/
  • New icon Meadow Lake Rd, between 18700 - 19900 blocks
    Alternating single lane closure Feb 7, 9am - 3pm. PUD - overhead maintenance at 7 locations. #20-101729MS
  • Robinhood Lane, between 13200 - 13100 and 128th Pl SE, between 17700 - 17500 blocks
    Single lane closure northbound continues through Feb 22, 9am - 3pm. CableCom - installing telecommunication equipment. #19-111055MS
  • New icon S. Machias Rd, in the 4300 block
    Single lane closure southbound Feb 17 - Feb 29, 9am - 3pm. PSE/InfraSource Services - installing gas service to a residence. #20-101988MS
  • S Machias Rd and Machias Cutoff Rd, at the intersection
    Intermittent shoulder and single lane closures Jan 20 - Feb 7, 9am - 3pm. Snohomish County Public Works - installing signal poles and mast arms for the new traffic signal at the intersection. PM Ingrid Earle, 425-262-2762 #19-108551MS
  • New icon Sunnyside Blvd, in the 900 block
    Daily FULL ROAD closure ( maximum 2 minute intervals) Feb 24 - Feb 25, 9am - 2pm. Olympic Pipeline - closures for trucks to enter and exit site for purge and repairs at the block valve. #20-101387MS/
  • 63rd Ave SE, in the 12900 block
    Alternating single lane closure Feb 12 - Feb 28, 9am - 3pm. PSE/InfraSource Services - installing gas service with patching and paving restoration to follow. #20-101531MS
  • New icon 91st Ave SE, in the 15300 block
    Alternating single lane closure revised Mar 9 - Mar 20, 9am - 3pm. PSE/InfraSource Services - installing gas service with patching and paving restoration to follow. #20-101626MS/
  • New icon 216th St SE, in the 8700 block
    Alternating single lane closure Feb 3 - Mar 13, 9am - 3pm. CC Edwards Construction - installing water, sewer and storm utilities and frontage improvements for RL Swanson short plat. #19-118188MS

Stanwood/ Silvana

   
  • No postings at this time. 

Sultan -Startup area

  • New icon Sultan Basin Rd and 124th St SE
    Single lane closure Feb 3 - Feb 6, 8am - 4pm. CC Edwards Construction - raise sewer manhole castings in conjunction with Sultan Public Sewer Main Extension. #19-105844MS
  • New icon 124th St SE,  at Sultan Basin Rd
    Single lane closure extended Feb 10 - Feb 28, 9am - 4pm. AA Asphalting - patching and paving restoration for the plat of Skyridge Estates. #19-115688MS
  • 363th Ave SE, in the 14200 block
    Single lane closure (northbound) will continue through Feb 13, 8am - 4pm. PSE/InfraSource Services - rebuilding PSE district regulator station. Patching and paving restoration work by AA Asphalting to follow. #19-114417MS

Tulalip


  • No postings at this time.

Woodinville

  • 76th Ave SE, at 23030
    Single lane closure southbound Jan 20 - Feb 7, 9am - 3pm. AA Asphalting - patching and paving restoration work following gas service installation. #20-101085MS