Meadowdale Design Phase

Snohomish County Parks and Recreation/Surface Water Management Div. of Public Works/Snohomish County Marine Resources Partnership



Project Description

This project includes preparing design drawings for permit submittal and final construction bid documents for the preferred alternative that was selected during the feasibility phase. The design consists of removing approximately 130
linear feet of railroad embankment and installing a four-span railroad bridge  Approximately 2 plus acres of created/restored estuary and riparian habitat enhancement is proposed with a second footbridge located over Lund's Gulch Creek. Paths will be relocated to provide viewpoints of the estuary. 

Lunds Gulch Creek Culvert under BNSF Railroad

Meadowdale Tunnel

Upcoming Meetings :

  • Community Meeting (TBD - possibly September 2016)

Related Link(s):

Current Status:
Design RFQs are due May 9, 2016. Contracts for successful firms/individuals are anticipated to be executed in June 2016. Preliminary geotechnical work and cultural resources investigation will commence in late May under two separate on-call contracts.


Related Documents:
Contact Person:  Logan Daniels, P.E., Parks Engineer
                                  Snohomish County Parks & Recreation

       Email: [email protected]