Project Description
Snohomish County Public Works will be constructing sidewalk improvements on three intersections along 128th Street between Fourth Avenue West and Eighth Avenue West. The purpose of the project is to provide pedestrian accessibility that meets current Americans with Disabilities Act (ADA) requirements. Improvements include replacing existing sidewalk ramps in the project vicinity and installing new ramps where needed.
Schedule
Construction is scheduled begin in October 2015. This project has an expected duration of six weeks.
Traffic Impact
During construction, signs will be placed in the area indicating pedestrian detour routes. Intermittent lane closures and construction work will occur in the project area from 9:30 a.m. to 2:00 p.m. and 8 p.m. to 4 a.m.