Drainage Improvements at Filbert Drive near 1st Avenue Southeast

Description - Completed 2016

The project improved the condition and capacity of drainage system along Filbert Dr between 1st Avenue and 2nd Avenue SE. The work consisted of upgrading 200 feet of storm sewer pipe, including 4 driveway culverts, and regrading approximately 600 feet of roadside ditches.


Schedule

Construction was completed in 2016 by Snohomish County Road Maintenance crew.


Traffic

Traffic Control/Project Notification: Signage and traffic control was provided to route traffic around the construction site. No full road closure occurred.