Description - Completed 2016

The project replaced and upgraded 589 LF of storm sewer pipe, one driveway culvert, and six catch basins to increase the drainage system capacity and alleviate road and private property flooding.


Schedule

Construction was completed in 2016 by Snohomish County Road Maintenance crew.


Traffic

Signage and traffic control was provided to route traffic around the construction site. No full road closure occurred.