Cathcart Way Bus Pullouts

April 2018 Update

Construction is anticipated to begin this month and be completed in July. Each bus pullout should take about two weeks to construct. During construction there will be single-lane closures during working hours. Pedestrian access will be limited, however pedestrian detour routes will be posted, if they are needed.


Description


Snohomish County Public Works will construct four new bus pullouts to serve the existing Community Transit (CT) route 109. Two will be constructed at Cathcart Way and Snohomish-Cascade Drive and two will be built at Cathcart Way and Puget Park Drive. The existing curb, gutter and sidewalk will be removed and new, wider pavement will be added to create the bus pullouts. New curb, gutter and sidewalk will be constructed. The bus pullouts will be approximately 10 feet wide by 110 feet long. Sections of rock wall will be used where needed. 

​ 
Snohomish-Cascade Drive


Proposed Improvements

Snohomish-Cascade Drive - February 2018

Schedule


Construction for this project is anticipated to be completed by late July. The bus stops are expected to become active shortly after construction is completed and will be posted on the route's webpage.

Traffic Impact


This project will require single-lane closures.

Funding


The preliminary cost estimate for this project is $250,000 and is funded by the county road fund.

Environmental Review


​Puget Park Drive

Proposed Improvements

Puget Park Drive - February 2018

Schedule


Construction for this project is anticipated to be completed by late July. The bus stops are expected to become active shortly after construction is completed and will be posted on the route's webpage.

Traffic Impact


This project will require single-lane closures.

Funding


The preliminary cost estimate for this project is $250,000 and is funded by the county road fund.

Environmental Review