- Home
- Your Government
- Community & Business Services
- Public Works
- Roads Central
- Current Road Projects
- County-Wide County Road Projects
- Advance Mitigation Site at Little Bear Creek
- Advance Mitigation Site at Little Bear Creek
Advance Mitigation Site at Little Bear Creek
Description - Completed
Snohomish County Public Works acquired four parcels of land in the lower Little Bear Creek Watershed near Woodinville. The 17 acres acquired was used as part of an advance mitigation effort. This project restored wetlands and stream habitat on the site, preserved other areas, and enhanced some areas to compensate for impacts associated with future roadway projects.
Restoration efforts required years of collaboration among county, federal, state, and local permitting agencies, local Tribes, and consulting design engineers at ESA Associates. Since work began in 2019, construction activities have:
- Removed 17 structures and associated utilities
- Decommissioned a domestic well and a hand dug well
- Cleared more than 4.25 acres of wetland fill
- Removed 0.86 acres of impervious surface area
- Removed approximately 1,200 linear feet of drain pipe and electrical conduit
- Enhanced soil with 2,300 cubic yards of compost and 4,000 cubic yards of wood chip mulch
- Installed more than 100 woody and boulder habitat features
- Created and/or enhanced 10 permanently or seasonally flooded shallow depressions to support wildlife
- Created a floodplain bench and two large wood structures to improve flood dispersion and provide refuge for juvenile salmonoids
- Enhanced two perennial tributary streams and acres of wetlands
- Planted more than 21,000 native trees and shrubs
The completed work is projected to save the county more than $450,000 in mitigation costs for the first two projects that will use the site (Alderwood Mall Parkway and 43rd Ave SE corridor improvement projects). A minimum of 10 other Public Works projects are expected to avoid or greatly reduce mitigation costs through credits generated in the future.
Public Works staff will continue to monitor the project area during the next 10 years to ensure that the site vegetation matures and other habitat features meet performance standards. The site will be protected in perpetuity and left in its natural state as a conservation area.
Schedule
- 2019: Demolition of buildings
- Summer 2022: Restoration construction
- Fall 2022: Installation of more than 21,000 native plants
Traffic Impact
There were single-lane closures at the intersection of 238th St SE and 58th Ave in July 2022. Crews re-graded the adjacent hill to improve site distance.
Funding
- Funding for this project was provided by the Snohomish County Road Fund.
Environmental Review
- An environmental review of the Little Bear Creek Advance Mitigation Site (RC 1730) was completed in compliance with the State Environmental Policy Act (SEPA). SEPA requires that all state and local agencies identify and evaluate the environmental impacts of their land use decisions. An Environmental Checklist was prepared and a Determination of Non-Significance was issued for this project. These documents are available by viewing the links below.
Documents
/documentcenter/view/108948/rc1730-asdesign-pse-plans
- LDA Decision and Permit - May 2021
- /documentcenter/view/108949/complete_little-bear-creek-advance-mitigation-site_oct21_2020 LBC Mitigation Plan October 2020
- LBC LDA and SEPA Postcard April 2019
- LBC SEPA DNS and SEPA Checklist
- LBC Site Plan Drawings
- Geologic Investigation and Geotechnical Investigation Report
- Hydrogeologic Report
- Baseline Conditions Report
Contact Us
-
Snohomish County Public Works
3000 Rockefeller Ave., M/S 607
Everett, WA 98201
Ph: 425-388-3488
-
Email the Roads Division
Ph: 425-388-ROAD (7623)