26th Dr SE Near 10423

Project Description


Snohomish County Public Works will be replacing 550 LF of 12 inch pipe along 26th Drive SE, and a culvert under 104th Pl SE. Ditches will be regraded as needed along 26th Dr. SE and 104th Pl SE. The project will improve working condition of this nonstandard and deteriorating drainage system to alleviate road and property flooding.

Schedule


Construction is scheduled to start on Oct. 15, 2018 and is expected to last approximately three weeks.

Traffic Impact


Appropriate detour route, signage, and traffic control will be provided to route traffic around the construction site. No full road closures are anticipated for this project. Property owners adjacent to the work area have been contacted and given project and Surface Water Management contact information.

Funding


The estimated construction cost for this project is $124,700.