Echo Lk Rd Culvert Replacement

Description - Completed


Snohomish County Public Works replaced a culvert under Echo Lake Rd July 12-15. The previous culvert was replaced with a 64-inch wide metal pipe arch culvert that will ease flooding on the road.

Schedule


The construction work took place July 12-15.

Traffic Impact


To install the new culvert, Echo Lake Rd was fully closed between 214th Pl SE and 215th Pl SE July 12-15. The road closure began Friday at 10 A.M. and ended Monday at 5 A.M. A signed detour route was posted. The detour route used Elliott Rd, Welch Rd, W Lost Lake Rd, and Lost Lake Rd.

Emergency services were notified of the project and were prepared to provide assistance to residents during the road closure.

Funding


This project cost estimate is $317,000 paid for through Surface Water Management Utility funds.