Rice Rd Culvert Replacement

Description - completed


Snohomish County Public Works replaced a culvert under Rice Rd (339th Ave SE) during summer 2020. The two previously existing culverts were undersized and were replaced with a single 24-inch corrugated plastic storm sewer pipe.

Schedule


The main construction work began on July 6 and finished on Sept. 17. The road was closed with a signed detour route. 

Traffic Impact


Rice Rd was closed in the 13400 block during construction. A signed detour route was posted. Emergency services were notified of the project and provided assistance to residents during the road closure.

Funding


This project cost estimate was $80,715 and was funded through the county Surface Water Utility funds.