Safe Kids, Improved Pathways (SKIP)
In partnership with local school districts, Snohomish County designed, constructed and funded 48 projects that provide children safe, accessible pathways to the 34 elementary schools in unincorporated Snohomish County. The projects were constructed from 2014 through 2018 and included widening shoulders, installing crosswalks and crossing beacons, and filling in gaps in walkways within one mile of elementary schools.
Projects Completed in 2017 and 2018
Elementary school | Project description | Status |
---|---|---|
Discovery Elementary shoulder | Construct 507 feet of pedestrian accessible shoulder on 116th St SE and pave 1,065 feet of shoulder on the west side of Silver Way (second phase of this project) / see map | Completed in 2018 |
Forest View Elementary shoulder | Construct an asphalt paved walkway on Sunset Rd between Strumme Rd and 161st SE /see map | Completed in 2017 |
Hazelwood Elementary Shoulder | Widen 500 feet of shoulder on the south side of 204th St SW near the school / see map. | Construction expected in summer 2018 |
James Monroe Elementary sidewalk | Construct curb returns on 110th St SE at 23rd Dr SE / see map | Completed in 2018 |
Martha Lake Elementary shoulder | Pave 123 feet on the west side of Larch Way from 181st Pl SW and north for 123 feet / see map | Completed in 2018 |
Odyssey Elementary shoulder | Pave 433 feet of shoulder on the north side of Gibson Road near Avondale Way / see map | Completed in 2017 |
sidewalk | Construct 70 feet of sidewalk on the south side of Grimes Rd from west of 7th Ave SE up to 7th Ave SE | Completed in 2018 |
Projects Completed in 2014, 2015 & 2016
Elementary school | Project description | Status |
---|---|---|
Canyon Creek Elementary beacon | Install a flashing beacon and marked crosswalks on 39th Ave SE / see map | Completed in 2016 |
Canyon Creek Elementary sidewalk | Reconstruct the curb return on the SE corner of 39th Ave SE at 209th Pl SE and construct curb and gutter to line up with the existing curb line on 39th Ave SE to the south / see map | Completed in 2016 |
Cathcart Elementary School shoulder | Constructed 2,600 feet of shoulder on the west side of 83rd Ave. NE from 188th St. SE to 180th St. SE | see map | Completed 2014 |
Cedar Woods Elementary sidewalk | Construct 125 feet of sidewalk on the east side of 35th Ave SE to fill a gap near 185th Pl SE / see map | Completed 2016 |
Cedar Wood Elementary shoulder | Paved 100 feet of shoulder on the north side of 169th St SE near 35th Ave SE. see map | Completed paving in 2014 |
Cedar Wood Elementary shoulder | Extended shoulder 300 feet along 35th Ave between 168th St. SE and 169th St. SE near Cedar Wood Elementary | See map | Completed June 2014 |
Cedar Wood Elementary sidewalk | Constructed 700 feet of sidewalk along 184th St SE between 36th Dr SE and 39th Dr SE/see map | Completed 2015 |
Chain Lake Elementary shoulder | Upgraded 1,750 feet of shoulder along the east side of Chain Lake Road from 127th St. SE to the elementary school. | See map | Completed Aug. 2014 |
Cougar Creek Elementary shoulder | Upgraded 575 feet of shoulder on the east side of 11th Ave NE in front of the school. | See map | Completed Sept. 2014 |
Discovery Elementary shoulder | Removed vegetation and installed gravel shoulder west side of Silver Way from 116th St. SE to the existing sidewalk; and along north side of 116th St. SE from Silver Way to Everett city limits | See map | Completed July 2014 |
Fernwood Elementary sidewalk | Construct 125 feet of sidewalk on the east side of 35th Ave SE to fill a gap near 185th Pl SE/see map | Completed 2016 |
Fernwood Elementary sidewalk | 700 feet of sidewalk along 184th St SE between 36th Dr SE and 39th Dr SE ISee map | Completed 2015 |
Hazelwood Elementary sidewalk | Construct 260 feet of curb, gutter and sidewalk on 204th St SW in front of Hazelwood school / see map | Completed 2016 |
Hill top Elementary shoulder | Constructed 870 feet of shoulder on the north side of Hubbard Road from Damson Road to 210th St SW. See map | Completed 2015 |
Hilltop Elementary Beacon | Installed two solar-powered flashing beacons at the two crossings on Damson Road | See map | Completed 2014 |
Jefferson Elementary shoulder | Construct 1200 feet of sidewalk on Burley Dr from Goblin Lane to Everett city limits / see map | Completed 2016 |
Jefferson Elementary sidewalk | Constructed 175 feet of sidewalk and pave 175 feet of shoulder along the south side of Burley Drive near Goblin Lane I see map | Completed 2015 |
Jefferson Elementary shoulder | Upgraded 650 feet of shoulder along west side of Goblin Lane; 200 feet along south side of Burley Drive from 24th Ave. SE to Goblin Lane; 800 feet along west side of 24th. Ave. from Burley Road to 96th PL. SE. | See map | Completed Oct. 2014 |
Lockwood Elementary beacon | Installed a flashing beacon on Locust Way near the school | See map | Completed October 2014 |
Machias Elementary shoulder | Expanded walkable shoulder 2,500 feet along OK Mill Road from the OK Mill bridge, left on 147th St. to Machias Elementary School. | See map | Completed June 2014 |
Maltby Elementary shoulder | Extended walkable shoulder on west side of 99th Ave Se from 216th St SE to Paradise Lake Road I see map | Completed 2015 |
Maltby Elementary accessible shoulder | Widened 380 feet of shoulder on the southside of 212th St SE near the school / see map | Completed 2015 |
Martha Lake Elementary sidewalk | Construct 550 feet of sidewalk, curb and gutter to fill in three sidewalk gaps on 6th Ave W between 170th Pl SW and 164th St SW / see map | Completed 2016 |
Maltby Elementary beacon | Installed a flashing beacon on 99th Ave SE at 215th Pl SE near the school / see map | Completed 2015 |
Maltby Elementary shoulder - 2 | Constructed 1,300 of shoulder along the west side of 95th Ave. SE from 212th St. SE to the end of the county road | see map | Completed 2014 |
Martha Lake Elementary pedestrian beacon | Installed a pedestrian beacon on Larch Way at the existing marked crosswalk in front of the elementary school. | See map | Completed Sept. 2014 |
Oak Heights accessible shoulder | Widen 720 feet of shoulder on the south side of Jefferson Way near the school / see map | Completed 2016 |
Oak Heights Elementary shoulder | Paved 260 feet of shoulder on the east side of 18th Ave W between Oak Road and 154th Pl SW I see map | Completed 2015 |
Oak Heights Elementary beacon | Installed a flashing beacon at both designated school crossings on 18th Ave W /see map | Completed 2015 |
Odyssey Elementary shoulder | Filled 765-foot sidewalk gap on west side of Admiralty Way between Manor Way and Gibson Road | See map | Completed Oct. 2014 |
Olivia Park accessible shoulder | Widen 1,095 feet of shoulder along the west side of 6th Ave W near the school / see map | Completed 2016 |
Picnic Point pedestrian beacons | Installed two flshing beacons at two school crossings on 140th St SW / see map | Completed 2015 |
Quil Ceda and Tulalip speed signs | Installed two solar-powered signs that tell drivers their speed along 27th Ave. NE north of 74th St. SE | See map | Completed Oct. 2014 |
Salem Woods Elementary shoulder | Upgraded 1,615 feet of shoulder along east side of Wagner Road from 132nd St. SE to Salem Woods Elementary | See map | Completed July 2014 |
Salem Woods Elementary phase 2 | Upgraded 2,250 feet of shoulder along east side of Wagner Road from Woods Creek Road to 132nd St. SE. | See map | Completed Aug. 2014 |
Seattle Hill Elementary School | Construct approximately 150 LF of sidewalk on the west side of 51st Ave SE from just north of 123rd St SE to just south of 122nd St SE/ see map | Completed 2016 |
Seattle Hill Elementary beacons | Installed flashing beacons at the designated school crossing on 51st Ave SE / see map | Completed 2015 |
Seattle Hill accessible shoulder | Widened 270 feet of shoulder on the east side of 51st Ave SE near the school. /see map | Completed 2015 |
Silver Firs Elementary beacons | Installed flashing beacons at the designated school crossings on Silver Firs Dr and Puget Park Dr / see map | Completed in 2015 |
Totem Falls Elementary beacons | Installed flshing beacons at the designated school crossing on Snohomish Cascade Drive / see map | Completed 2015 |
Totem Falls raised crossing | Installed raised pedestrian crossing at existing sidewalk on Cascade Drive near Totem Falls Elementary | See map | Completed spring 2014 |
* For a list of current road construction projects, please visit the Roads Update page.