Snohomish County Public Works is proposing to construct Interurban Trail Improvements between 160th St SW and 167th Pl SW. This project will construct missing links in the Interurban Trail for approximately 0.5 mile. The purpose is to provide continuous facilities for pedestrians and bicycles through the corridor.

Schedule


  • 2021-2022 - design, survey, environmental review and right of way plan 
  • 2023 - right of way acquisition
  • 2024 - proposed construction

Traffic Impact


Traffic impacts will be determined in the project engineering phase.

Funding


Snohomish County Road Funds will be used for design, engineering, right of way acquisition and part of the construction costs. Additional funding sources are being pursued.