Whitehorse Campground Phase 2

  1. 1
  2. 2

Project Description

Phase 2 is the addition of 12 non-utility campsites (with shared water) and shower-equipped restrooms at Whitehorse Park campground. Construction is scheduled for summer 2022 with an estimated completion date of fall 2022. Most work will be performed on weekdays between the hours of 8 am-5 pm. Existing (Phase 1) campsites will remain open during construction but may be impacted by noise and equipment traffic.  


Current Status

Updated 11/16/22

  • The restroom foundation has been completed and the basic structure has been built. Because we were able to build the concrete masonry unit (CMU) block walls before freezing temperatures, we will be able to build and finish the restroom in time for the 2023 camping season.
  • All materials for the pre-engineered building have been delivered to the site.
  • Picnic tables and fire pits will be installed by county maintenance before we open the park in spring 2023.
  • The 12-site campground loop has been completed.