Snohomish County Public Works is scheduled to overlay 132nd St SE/134th Pl SE/Cathcart Way from Seattle Hill Road to SR 9 during spring and summer of 2024. The overlay will preserve 3.12 miles of pavement and make for a smoother driving surface for motorists.
This project will extend the useful life of the roadway by grinding away the existing top layer, performing pavement repair, and then overlaying the asphalt. It will also upgrade pedestrian facilities with 55 ADA compliant curb ramps and install conduit for future Accessible Pedestrian Signals (APS) installation.
Cost: $5.6 million for construction
The 132nd St SE/134th Pl SE/Cathcart Way overlay/paving project from Seattle Hill Rd to SR 9 is federally funded through:
Ph: 425-262-2437
View additional road information.
Project #RC1797
Construction schedules are subject to change based on many factors that include: public safety; availability of funding, staffing, equipment and materials; right of way issues; permitting requirements; coordination with utilities and other agencies; soil conditions under roadway and seasonal changes.