132nd St SE / 134th Pl SE / Cathcart Way (Seattle Hill Rd to SR 9)
Description
Snohomish County Public Works is scheduled to overlay 132nd St SE/134th Pl SE/Cathcart Way from Seattle Hill Road to SR 9 during spring and summer of 2024. The overlay will preserve 3.12 miles of pavement and make for a smoother driving surface for motorists.
This project will extend the useful life of the roadway by grinding away the existing top layer, performing pavement repair, and then overlaying the asphalt. It will also upgrade pedestrian facilities with 55 ADA compliant curb ramps and install conduit for future Accessible Pedestrian Signals (APS) installation.
Schedule
Engineering and design: 2022-2023
Construction: spring and summer 2024
Traffic Impact
Single-lane closures will be a part of this project
Night construction possible with this project but one lane will remain open in each direction, minimizing impact to drivers
Access to businesses and sidewalks will be maintained
Funding
Cost: $5.6 million for construction
The 132nd St SE/134th Pl SE/Cathcart Way overlay/paving project from Seattle Hill Rd to SR 9 is federally funded through: